Сonstruction progress
Video Report March 2020

Progress in the construction of the residential complex

  • The first 2 sections at the check-in stage
  • Work in 3,4,5 sections

Video report NOVEMBER 2019

Progress in the construction of the residential complex

  • The first 2 sections at the check-in stage
  • Work in 3,4,5 sections

Video Report NOVEMBER 2019

Progress in the construction of the residential complex

  • The first 2 sections at the check-in stage
  • Active improvement of the local area
  • Equipment for sports fields at the completion stage

Construction report for 08/20/2019

3 stage of construction:

  • Facade work completed 90%
  • The installation of inter-apartment partitions
  • Installation of internal communications is underway

4th stage of construction:

  • All monolithic work completed to 3 floors
  • Installed vertical elements of 4 residential floors

5 phase of construction

  • Excavation of the pit completed

Construction video report - 08/19/19

3 stage of construction:

  • Facade work completed 90%
  • The installation of inter-apartment partitions
  • Installation of internal communications is underway

4th stage of construction:

  • All monolithic work completed to 3 floors
  • Installed vertical elements of 4 residential floors

5 stage of construction:

  • Excavation of the pit completed